brighton logo
 
 

Falmer from Afar - Amex Stadium November 2010

Not even freezing weather can detract from the beauty of what is developing on Village Way, Falmer as we returned for our first visit in six weeks before setting off for the Southampton away game.

The exterior of the North Stand is now completed, and preparation work appears to be beginning on the pitch as the surface is dug up.

The concourses of the South Stand appear to be nearly done, and the brickwork in the south-west corner, the main vantage point into the ground, is now beginning to be put up meaning it won't be long until you can no longer see in.

Add to this the ongoing bridge work and the beginning of construction on ramps and walkways and it really does hit home that in just eight months time we will be calling the Amex home.